Question: A time study was conducted on a task that consists of four elements. The observations and performance ratings for six cycles are shown in the
A time study was conducted on a task that consists of four elements. The observations and performance ratings for six cycles are shown in the following table.
| Observations (minutes per cycle) | |||||||
| Element | Performance Rating | 1 | 2 | 3 | 4 | 5 | 6 |
| 1........... | 90% | 0.44 | 0.50 | 0.43 | 0.45 | 0.48 | 0.46 |
| 2........... | 85 | 1.50 | 1.54 | 1.47 | 1.51 | 1.49 | 1.52 |
| 3........... | 110 | 0.84 | 0.89 | 0.77 | 0.83 | 0.85 | 0.80 |
| 4........... | 100 | 1.10 | 1.14 | 1.08 | 1.20 | 1.16 | 1.26 |
- Calculate the average time for each element.
- Calculate the normal time for each element.
- Assuming an allowance factor of 15 percent of workday, calculate the standard time for this task.
Step by Step Solution
There are 3 Steps involved in it