Question: A time study was made of a job to develop new time standards. A worker was observed for 30 minutes. During that time, 40 units

A time study was made of a job to develop new
A time study was made of a job to develop new time standards. A worker was observed for 30 minutes. During that time, 40 units were produced. The analyst rated the worker as performing at a 120 percent performance rate. What is the normal time for this task? 0.80 minutes per unit 0.90 minutes per unit 1.00 minutes per unit 1.20 minutes per unit 1.33 minutes per unit