Question: A toy car will be made that costs two headlights (LD) and three taillights (LT). The headlights consist of a filament (Fil) and two connectors
A toy car will be made that costs two headlights (LD) and three taillights (LT). The headlights consist of a filament (Fil) and two connectors (Con). The taillights consist of two filaments (Fil) and two special connectors (ConES).
Make the Product Structural Tree
If it is required to manufacture 100 cars, what is the material requirement (BOM)?
| Headlights (LD) | Quantity to ask for 100 cars |
| TailLights (LT) |
|
| Filaments (Fil) |
|
| connectors (Con) |
|
| Especial connectors (ConEs) |
|
|
|
|
|
|
|
Complete the following table according to the established times (L / T Lead Time) to manufacture 100 cars.
| DAYS | 1 | 2 | 3 | 4 | 5 | 6 | 7 |
| |
| CAR | Required Date |
|
|
|
|
|
|
| L/T = 1 DAY |
| Order Placement |
|
|
|
|
|
|
| ||
| LD | Required Date |
|
|
|
|
|
|
| L/T = 2 DAYS |
| Order Placement |
|
|
|
|
|
|
| ||
| LT | Required Date |
|
|
|
|
|
|
| L/T = 2 DAYS |
| Order Placement |
|
|
|
|
|
|
| ||
| FIL | Required Date |
|
|
|
|
|
|
| L/T = 3 DAYS |
| Order Placement |
|
|
|
|
|
|
| ||
| CON | Required Date |
|
|
|
|
|
|
| L/T = 1 DAY |
| Order Placement |
|
|
|
|
|
|
| ||
| ConES | Required Date |
|
|
|
|
|
|
| L/T = 1 DAY |
| Order Placement |
|
|
|
|
|
|
| ||
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts