A two lane two way road is at present carrying a traffic of 1000 CVD. It is
Fantastic news! We've Found the answer you've been seeking!
Question:
A two lane two way road is at present carrying a traffic of 1000 CVD. It is to be strengthened for growing traffic needs. The VDF had been found to be 3.0 The rate of growth of traffic is 10% per annum. The period of construction is 5 years. The pavement is to be designed for 15 years after completion. Calculate the cumulative standard axles to be used in design.