Question: A) Use Excel to prepare a Gantt Chart for the project, making sure to show any slack for all activities. begin{tabular}{|c|l|c|c|} hline Task ID &

A) Use Excel to prepare a Gantt Chart for the project, making sure to show any slack for all activities.

A) Use Excel to prepare a Gantt Chart for the

\begin{tabular}{|c|l|c|c|} \hline Task ID & Task Description & Immediate Predecessor & Duration \\ \hline A & Start story draft using template & & 7 \\ \hline B & Research client firm & & 5 \\ \hline C & Create "due diligence" rough draft & A, B & 5 \\ \hline D & Coordinate needs proposal with client & C & 20 \\ \hline E & Estimate future demand and cash flows & C & 11 \\ \hline F & Draft future plans for client company & E & 8 \\ \hline G & Create and approve legal documents & C & 12 \\ \hline H & Integrate all drafts into first-draft proposal & D, F, G & 6 \\ \hline I & Line up potential sources of capital & F, G & 9 \\ \hline J & Check, approve and print final legal proposal & H & 5 \\ \hline K & Sign contracts and transfer funds & I, J & 30 \\ \hline \end{tabular}

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!