Question: A) Use the data given above to answer this question. What is the critical path? Select one: a. A-C-D b. A-D-C c. D-E-F d. A-D-F

A) Use the data given above to answer this

A) Use the data given above to answer this question. What is the critical path?

Select one:

a. A-C-D

b. A-D-C

c. D-E-F

d. A-D-F

B)

The distance between different possible routes are shown in the table below.

How many arcs would you use in drawing the network diagram for this problem?

Path Distance

1 to 2 3 1 to 3 2 2 to 4 4 2 to 5 5 3 to 4 3 3 to 5 7 4 to 6 6 5 to 6 2

Select one:

a. 6

b. 7

c. 8

d. 2

a 5 A schedule of activities is presented below Preceding Time (days) Activity Activity Regular Crash 10 5 b 7 4 b 3 2. d 4 2 6 3 f cd 5 2 Cost Regular 5,000 3,000 2,000 5,000 5,000 4,000 3 Crash 10,000 8,000 4,000 6,000 7,000 8,000 a e What is the expected time to complete the project using the regular times? Solve using Management Scientist. You do not need to be concerned with crash costs for the project

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!