Question: a) Use the following information for project Delta and construct the network diagram with respective activity node labels (see below requirement) and identify the critical
a) Use the following information for project Delta and construct the network diagram with respective activity node labels (see below requirement) and identify the critical path in bold (12 marks

Question 3 a) Use the following information for project Delta and construct the network diagram with respective activity node labels (see below requirement) and identify the critical path in bold (12 marks) Activity Description Predecessors Estimated Duration A Contract signing None 5 B Questionnaire design A C Target market ID A D Survey sample B. C 13 E Develop presentation B F Analyze results D G Demographic analysis C 9 H Presentation to client E, F. G Early Identifier number Early start finish Activity Activity descriptor float Late Activity Late Start duration finish