Question: A. Using capacity planning with overall factors , estimate the labor hours needed in each work station for the next 3 weeks. B . Using
A. Using capacity planning with overall factors, estimate the labor hours needed in each work station for the next 3 weeks. B. Using capacity Bills, estimate the labor hours needed in each work center for the next three weeks.
7. Consider the following capacity planning data (Manufacturing lead times for A and B o Routings and time standards (i.e. same week as requirements): Set-up Time Set-up Time Product Work Center Std time Product Work Center (per week) 4 hr/unit WC28 hr/unit 7 hr/unit 2 hr/unit WC1 WC1 WC2 WC1 WC2 20 hrs 25 hrs 35 hrs 40 hrs WC1 WC2 Historical Work Center Percentages WC1 WC2 60% 40% Master Production Schedule Wk 1 200 Wk 2 150 100 Wk 3 200 150 125 S uith overall factors, estimate the labor hours needed in each work center