Question: A vendor submits a high - level project schedule for a three - year project, including a detailed design - phase schedule. What does this

A vendor submits a high-level project schedule for a three-year project, including a detailed design-phase schedule. What does this describe?
A. Rolling wave planning
B. Decomposition
C. Expert judgment
D. Templates