Question: A wage incentive plan pays workers a daily wage at a rate of $ 1 5 . 0 0 / hr multiplied by the number

A wage incentive plan pays workers a daily wage at a rate of $15.00/hr multiplied by the
number of standard hours accomplished during the shift. One worker-machine task in the
plant includes worker-paced elements totaling a normal time of 1.00 min and machine-
paced elements with a time of 3.00 min. The PFD allowance is 15%.Which is fair? A PFD allowance of 15% equates to a lost time per day of 62.6
min in an 8-hour shift, which leaves an actual working time of 417.4 min. Of this time,
machine time took 115 cycles x 3.00 min/cycle 345 min, which leaves 417.434572.4 Determine the stan-
dard time for the task given that (a) Am 0 and (b) Am 30%.(c) What does a worker
earn for the day under each policy if he or she produces 115 parts that day?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!