Question: A WBS with approximately 1 7 5 activities including: * Milestones * Summary * Activities ( LOE ' s , submittals, approval, procurement of long

A WBS with approximately 175 activities including:
* Milestones
* Summary
* Activities (LOE's, submittals, approval, procurement of long-lead items, and construction).
Since I have not experience in construction, I have been working hard creating the WBS and trying to make the proper logic.
Please see below my WBS:
1. Initial Phase
1.1 Submittals.
1.2 Review and approvals
2. Procurement phase
2.1 Procurement of Long lead items.
3. Site Preparation
3.1 Site Survey and analysis
3.2 Demolition phase
3.3 Site clearing
3.4 Grubbing
3.5 Site grading
3.6 Excavation
3.7 Eartwork
3.8 Erosion control and stormwater management
3.9 Utility installation
4. Foundations
4.1. Foundation design
4.2. Foundation construction
4.3. Concrete pouring
5. Superstructure
5.1. Structural framing
5.2. Floor Construction
5.3. Wall Construction
5.4. Roof System Construction
5.5. stairs installation
5.6. Doors & window installation
6. Exterior work
6.1. Exterior finishes
6.2. Roofing installation
6.3. landscaping and hardscaping
6.3.1. Construction of parking areas
6.3.2. paving pathways
6.3.3. Installation of Outdoor Amenities
6.4. exterior painting & finishes
7. Interior Work
7.1 Interior wall framing
7.2 Plumbing rough-in work
7.3 Electrical rough-in work
7.4 HAVC rough-in work
7.5 Flooring sub-floor installation
7.6 Flooring installation
7.7 insulation installation
7.8 Drywall installation
7.9 Interior finishes (flooring, painting, trim work, etc)
7.10 Fixtures and appliances
7.11 Final cleaning
8. Utility and services
8.1 Utility installation (water, sewer, electricity, telecom)
8.2 HVAC installation
8.3 Fire Protection System Installation
9. Furniture and equipment
9.1 Installation of furniture and equipment.
10. Commissioning & handover
10.1 system testing
10.2 final inspection & deficiencies
10.3 handover & documentation.
- Based on my WBS, what would you add or change or modify the sequence of the things?
- Based on the WBS, could you help with approximately 175 activities with the proper sequence and logic and maybe the times of each activity?.
- As you may notice we started the WBS with submittals because we are assuming that we already have the Notice to proceed.
- Could you please help me with milestones?
- Could you help me with 15 long lead items products?
Please don't submit anything from chatgpt
See below the actual picture of the request.
A WBS with approximately 1 7 5 activities

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!