Question: a) What is the completion time for the project? b) You are asked to shorten the project by three weeks. If you shorten it by

a) What is the completion time for the project?
b) You are asked to shorten the project by three weeks. If you shorten it by three weeks you will be given a bonus of $1,000. After you shorten the project by one week, is there more than one critical path? Yes or No.
c) You are asked to shorten the project by three weeks. If you shorten it by three weeks you will be given a bonus of $1,000. After you shorten the project by two weeks, is there more than one critical path? Yes or No.
d)You are asked to shorten the project by three weeks. If you shorten it by three weeks you will be given a bonus of $1,000. After you shorten the project by three weeks, what is the earliest finish time of activity I? what is the slack time in activity H? and what is your minimum cost to shorten it?