Question: a. What is the minimum-cost schedule for this project? b. What is the difference in total project costs between the earliest completion time of the

a. What is the minimum-cost schedule for this project?
b. What is the difference in total project costs between the earliest completion time of the project using "normal" times and the minimum-cost schedule you derived in part (a)?
You are the manager of a project to improve a billing process at your firm. The table below contains the data you will need to conduct a cost analysis of the project. Indirect costs are $1,000 per week, and penalty costs are $800 per week after week 12
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
