Question: a . What is the workstation cycle time required to produce 1 , 0 0 0 units per day? b . Balance the line using

a. What is the workstation cycle time required to produce 1,000 units per day?
b. Balance the line using the longest task time based on the 1,000-unit forecast, stating which tasks would be done in each workstation.
c. For part (b), what is the efficiency of your line balance, assuming it is running at the cycle time from part (a)?
d.After production was started, Marketing realized that it understated demand and must increase output to 1,100 units. What action would you take? Be specific and quantitative in your answer.