Question: a What will the third step be for assigning a person or equipment work resource to a task? Right-click the view bar on the left

a

What will the third step be for assigning a person or equipment work resource to a task? Right-click the view bar on the left edge of the Project window, and then click the name of the task view the users want to use as they make their assignments. B O On the Resource tab, in the Assignments group, click Assign Resources. Cc O In the Assign Resources dialog box, click the name of the work resource user want to assign to the selected task. D O In the Gantt Chart or other task view, click the task to which the user wants to assign a work resource

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Mathematics Questions!