A Work Breakdown Structure has been completed. The project team is now collecting estimated activity duration times
Fantastic news! We've Found the answer you've been seeking!
Question:
A Work Breakdown Structure has been completed. The project team is now collecting estimated activity duration times so that a schedule can be created. To estimate each activity several people who are responsible for completing the activities in the project are asked for time estimates. But as the team collects these estimated times they find considerable variance from one persons estimate to anothers Some have been more ambitious than others in determining what needs to be done. Which additional document would help clarify the situation?
Review Later
Risk Breakdown Structure
Schedule
Scope Statement
Business Case
Posted Date: