Question: A work breakdown structure indicates a task with fixed work of 1 6 hours and one resource assigned. Assuming the project uses a standard 4

A work breakdown structure indicates a task with fixed work of 16 hours and one resource assigned. Assuming the project uses a standard 40-hour workweek calendar, Which of the following is true?
Group of answer choices
Adding a second resource would increase the duration
Adding a second resource would decrease the duration
Adding a second resource would double the work
Adding a second resource would decrease the work