Question: A work breakdown structure indicates a task with fixed work of 1 6 hours and one resource assigned. Assuming the project uses a standard 4
A work breakdown structure indicates a task with fixed work of hours and one resource assigned. Assuming the project uses a standard hour workweek calendar, Which of the following is true?
Group of answer choices
Adding a second resource would increase the duration
Adding a second resource would decrease the duration
Adding a second resource would double the work
Adding a second resource would decrease the work
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
