Question: A work center assigns tasks to 4 work stations. The total of all the task times is 6.1 . If the cycle time used is

A work center assigns tasks to 4 work stations. The total of all the task times is 6.1 . If the cycle time used is 2.3 , what is the efficiency of this configuration? (Round your answer to 1 decimal places.)
Step by Step Solution
There are 3 Steps involved in it