Question: A work system consists of five sequential stations with process times 6 , 2 , 3 , 5 and 4 minutes respectively. What is the

A work system consists of five sequential stations with process times 6,2,3,5 and 4 minutes respectively. What is the bottleneck time? assume that market demand exceeds available capacity.