Question: A work system has six stations that have process times of 1 0 , 8 , 5 , 1 2 , 1 0 , and

A work system has six stations that have process times of 10,8,5,12,10, and 15 minutes. What is the bottleneck time (measured in minutes)?
60
10
15
50
12