Question: A worker takes 80 hours to do a job for which time allowed is 100 hours. Wage rate is 2.50 per hour. Calculate the works

A worker takes 80 hours to do a job for which time allowed is 100 hours. Wage rate is 2.50 per hour. Calculate the works cost of the job under the following methods of payment of wages : (i) Time rate, (ii) Halsey plan, (iii) Rowan pan. Additional information : (a) Material cost is 120, (b) Factory overhead is 125% of wages
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts