Question: A workshop has 4 machines and each unit needs to pass through each machine to be completed: machine 1+machine 2machine 3-machine 4 The capacity

A workshop has 4 machines and each unit needs to pass through each machine to be completed: machine 1+machine 2machine 3-machine 4 The capacity of the machines are as follows, 10, 25, 60, and 55 units per hour. What is the process cycle time of the system in minutes? Note: Round your final answer to two decimal places.
Step by Step Solution
There are 3 Steps involved in it
Machine Machine Machine Machine l6 uuithr 25 uithr 55 unithr Gouit hr First of all Calculate ... View full answer