Question: A=15, B=10, C=6, D=8,E=15 Please Explain work Search A PERT diagram for a project is given below: D ? 0 10 Start 0 10 End

A=15, B=10, C=6, D=8,E=15 Please Explain work
A=15, B=10, C=6, D=8,E=15
Please Explain work
Search A PERT diagram for a project is given below: D ? 0 10 Start 0 10 End B E Assume that activity times of Start and End are zero. Activity times for each activity is given in the data table below. a. Calculate each "?" in the PERT diagram. (20 ?'s, 0.3 pts each, 6 pts total) b. Determine the critical path.(1 pts) Data Table