Question: A4 A3 A6 AZ A8 A1 A2 A5 Consider the AON graph of a project shown above. The activity times are 3,4, 1, 5, 8,

A4 A3 A6 AZ A8 A1 A2 A5 Consider the AON graph of

A4 A3 A6 AZ A8 A1 A2 A5 Consider the AON graph of a project shown above. The activity times are 3,4, 1, 5, 8, 1, 2, 4 days for activities A1 through A8 respectively. What is the earliest completion time of the project? days