Question: AA A ezto.mheducation.com C Week 5: Quiz i Saved Help Save & Exit Submit Kerekes Manufacturing Corporation has prepared the following overhead budget for next

AA A ezto.mheducation.com C Week 5: Quiz i Saved Help Save & Exit Submit Kerekes Manufacturing Corporation has prepared the following overhead budget for next month. Activity level 3,500 machine- hours Variable overhead costs: 2.5 Supplies $19, 250 points Indirect labor 32, 900 Fixed overhead costs: Supervision 16, 700 Utilities 6, 900 Book Depreciation 7 , 900 Total overhead cost $83, 650 The company's variable overhead costs are driven by machine-hours. What would be the total budgeted overhead cost for next month if the activity level is 3,400 machine-hours rather than 3,500 machine-hours? Multiple Choice O $81,470 O $81,260 O $82,160 $83,650