Question: AA ezto.mheducation.com k 7: Quiz O a ezto.mheducation.com Saved Help Costs associated with two alternatives, code-named Q and R, being considered by Albiston Corporation are

AA ezto.mheducation.com
k 7: Quiz O a ezto.mheducation.com Saved Help Costs associated with two alternatives, code-named Q and R, being considered by Albiston Corporation are listed below: Supplies costs Power costs Inspection costs Assembly costs Required: Alternative Q $74, $34,200 $27 , $39, ooo Alternative R $74,000 $33,400 $33,400 $39,000 look a. Which costs are relevant and which are not relevant in the choice between these two alternatives? b. What is the differential cost between the two alternatives? a. Supplies costs Power costs Inspection costs Assembly costs b. Differential cost