Question: Abagail Corp. uses activity-based costing system with three activity cost pools. The following information is provided: Costs: Wages and salaries $ 208,000 Depreciation 109,000 Utilities
Abagail Corp. uses activity-based costing system with three activity cost pools. The following information is provided:
Costs: Wages and salaries $ 208,000
Depreciation
109,000
Utilities
117,000
Total
$440,000
Activity Cost Pools
Assembly
Setting Up
Other
Wages and salaries
0.59
30%
10%
Depreciation
0.40
45%
20%
Utilities
0.24
40%
30%
How much total cost would be allocated to the Assembly activity cost pool?