Question: ABC Builders submitted its first Pay Request on March 31, 2023, for the partially completed work on a project started on 01-01-2023. Upon receiving the
ABC Builders submitted its first Pay Request on March 31, 2023, for the partially completed work on a project started on 01-01-2023. Upon receiving the payment, the company plans to pay the following: Labor for its subcontractors $180,000, for March 2023. Consultants Fee, for each month from the start of 2023, $50,000 Monthly Equipment Lease $25,000 Monthly Utilities $ 10,000 Monthly Materials $30,000 How much would be the Net Worth of the company on
Step by Step Solution
There are 3 Steps involved in it