Question: ABC co. has the following data: Standard batch level material costs of Rs. 12,000 for a batch of 100 units. Static budget was for 180

ABC co. has the following data: Standard batch level material costs of Rs. 12,000 for a batch of 100 units. Static budget was for 180 units. Actual was Rs. 11,000 for a production of 80 units. Calculate the static budget or planning variance. (Note: this is a batch level cost)

Rs. 1,000 (unfavourable)

Rs. 12,000 (Favourbale)

Rs. 11,000 (Favourable)

Rs. 1,000 (favourable)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!