Question: ABC Construction has two projects starting next month. The projects are located within 15 miles of each other. One is a $3,000,000 project lasting 9
ABC Construction has two projects starting next month. The projects are located within 15 miles of each other. One is a $3,000,000 project lasting 9 months, and the other is a $500,000 project lasting 6 months. One project manager can handle both jobs, which will save money. An additional supervisor must be hired to avoid delays. What is the PMT exercising in this case?
| Resource allocation of salaried staff to multiple projects by adding a new supervisor to the team to improve work efficiency and avoid delays |
| Labor resource leveling of multiple projects to minimize cost by sharing salaried staff |
| Financial resource allocation and best use of the salaried staff available |
| Material and financial resource leveling and best use of salaried staff available |
Step by Step Solution
There are 3 Steps involved in it