Question: ABC Industry operates 6 days a week. There are two 8-hours shifts each day, with a half-hour break for lunch in each shift. The plant
ABC Industry operates 6 days a week. There are two 8-hours shifts each day, with a half-hour break for lunch in each shift. The plant is shut down on Sundays for regular maintenance.
The weekly demand for the product is 720 units. What is the TAKT time? (4 marks)