Question: Abdullah, a project manager, is currently working with his team to develop a project schedule for an IT project by estimating the number of work

Abdullah, a project manager, is currently working
Abdullah, a project manager, is currently working with his team to develop a project schedule for an IT project by estimating the number of work periods required to complete individual activities. The process that they are undertaking is: O a Sequencing activities. b. Estimating activity resources. O c. Defining activities. O d. Estimating activity durations