Question: able11.9Normal and Crash Data for General Foundry, Inc. TIME (WEEKS) COST ($) ACTIVITY NORMAL CRASH NORMAL CRASH CRASH COST PER WEEK($) CRITICAL PATH A 2
able11.9Normal and Crash Data for General Foundry, Inc.
TIME (WEEKS) COST ($)
ACTIVITY NORMAL CRASH NORMAL CRASH CRASH COST PER WEEK($) CRITICAL PATH
A 2 1 22,000 23,000 1,000 YES
B 3 1 30,000 34,000 2,000 NO
C 2 1 26,000 27,000 1,000 YES
D 4 3 48,000 49,000 1,000 NO
E 4 2 56,000 58,000 1,000 YES
F 3 2 30,000 30,500 500 NO
G 5 2 80,000 86,000 2,000 YES
H 2 1 16,000 19,000 3,000 YES
General Foundry's project crashing data are shown inTable11.9. Crash this project to 13 weeks using CPM. What is the final time for each activity after crashing?