Question: According to project estimation guidelines, each task estimate is supposed to be done independently of other tasks. Why does this lead to inaccurate estimates? Multiple

According to project estimation guidelines, each task estimate is supposed to be done independently of other tasks. Why does this lead to inaccurate estimates?
Multiple choice question.
Task interdependencies influence actual time and cost requirements.
Task hand-offs take less time than expected.
Work on tasks is completed independently, then handed off.