Question: According to Project Management. Complete the table below reflecting the forward and backward pass of this project. Simply list the question number with the answer
According to Project Management.
Complete the table below reflecting the forward and backward pass of this project. Simply list the question number with the answer next to it - For example 3.3.1. 10 (10)
| Activity | DURATION | ES | EF | LS | LF |
| START | 0 | 0 | 0 | 0 | 0 |
| A | 2 | 0 | 3.3.1 | 12 | 15 |
| B | 5 | 0 | 5 | 0 | 3.3.2 |
| C | 1 | 0 | 1 | 3.3.3 | 12 |
| D | 10 | 5 | 15 | 5 | 3.3.4 |
| E | 6 | 15 | 3.3.5 | 15 | 18 |
| F | 3 | 3.3.6 | 7 | 3.3.7 | 18 |
| G | 8 | 18 | 3.3.8 | 3.3.9 | 26 |
| End | 0 | 26 | 26 | 26 | 3.3.10 |