Question: According to project management experts, _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ is a technique whereby information
According to project management experts, is a technique whereby information from a similar past project is used to estimate the cost and duration of a planned project.
a Bottomsup estimating
b Rear mirror budgeting
c Forensic estimating
d Analogous estimating
e Forwardlooking budgeting