Question: According to Snapshot from Practice 6.2, if the project schedule begins to slip, it is the ________ you should focus on to get the project
According to Snapshot from Practice 6.2, if the project schedule begins to slip, it is the ________ you should focus on to get the project back on schedule. Multiple Choice least expensive activities most expensive activities noncritical activities critical activities near-critical activities