Question: According to the bar chart schedule, if task # 2 had required only half of the projected time to complete and the remainder of the

According to the bar chart schedule, if task #2 had required only half of the projected time to complete and the remainder of the project schedule had been adjusted by the amount of time saved on task #2, how much sooner would implementation of the Training Project occur?
a.1.5 weeks
b.2.5 weeks
c.3 weeks
d.3.5 weeks