Question: According to the data in the table below, what is the minimum expected completion time for the project? Activity Immediate Predecessor Optimistic Time Most Likely

According to the data in the table below, what is the minimum expected completion time for the project? Activity Immediate Predecessor Optimistic Time Most Likely Time Pessimistic Time A - 2 8 14 B - 8 8 8 C A 6 9 18 D B 5 11 17 Group of answer choices 18 19 37 11