Question: According to the punctuated - equilibrium model, groups experience a transition halfway between the first meeting and the official deadline A . when the project
According to the punctuatedequilibrium model, groups experience a transition halfway between the first meeting and the official deadline
A when the project time frame is longer than months
B when the project time frame is longer than weeks
C regardless of the length of the project time frame
D when the project time frame exceeds a year in length
E when the project time frame is longer than months