A network maintenance project is planned for the university. The following table shows the particular activities,...
Fantastic news! We've Found the answer you've been seeking!
Question:
Transcribed Image Text:
A network maintenance project is planned for the university. The following table shows the particular activities, normal (expected) times, activity variances, crash times, and additional crash costs. For example, Activity B has a normal time of 12 days and can be crashed down to a minimum of 6 days for an additional cost of $1400 per day on top of the Normal Cost. Note that, normal (expected) times and activity variances are already calculated for you from the optimistic, most likely, and pessimistic time estimates assuming that each activity time follows an independent Beta distribution. Precedence relationship is demonstrated with the project network below. Using the given table and the project network, please answer the following questions: Activity A B C D E F G H 1 J K Normal Time (days) 9 12 18 9 6 6 6 6 7 6 8 Variances Activity Crash Time Crash Cost (days) (5) per day 7 1200 1400 900 1000 1350 1500 650 1700 1100 575 2500 6.25 9 9 5.0625 0.4444 0.6944 0 5.0625 9 8 16 8 4 5 4 5 5 4 5 START B 0 12 12 1 13 A 0 9 90 9 C018 18 0 18 Trial # E 12 18 6 13 19 D 9 18 99 18 G 18 24 6 20 26 F 18 24 6 19 25 H 18 24 6 18 24 Critical Path's before crashing LEGEND ID ES EF LS LF 124 31 725 32 K 24 32 8 24 32 Completion Time (before crashing) J 24 30 6 26 32 a) What is the probability that the project will take 30 to 37 days to complete? b) What project completion time should the project manager set as a goal to her team in order to be 87.50% confident that the project will be completed within that time frame? Your answer can be in days and you can provide the result in decimals. c) Suppose that for every day the project is shortened the maintenance firm will be awarded $3,500. What activities should be crashed and by how many days? Show your work using the table given below. At each trial reduce the project duration by one day stating which activity/ies should be crashed and how much it will cost to crash this activity/ies LINIS: Use the following table to answer. Add as many rows as you need and completely fill the table please H Activityles to be Crashed Crash Cost A network maintenance project is planned for the university. The following table shows the particular activities, normal (expected) times, activity variances, crash times, and additional crash costs. For example, Activity B has a normal time of 12 days and can be crashed down to a minimum of 6 days for an additional cost of $1400 per day on top of the Normal Cost. Note that, normal (expected) times and activity variances are already calculated for you from the optimistic, most likely, and pessimistic time estimates assuming that each activity time follows an independent Beta distribution. Precedence relationship is demonstrated with the project network below. Using the given table and the project network, please answer the following questions: Activity A B C D E F G H 1 J K Normal Time (days) 9 12 18 9 6 6 6 6 7 6 8 Variances Activity Crash Time Crash Cost (days) (5) per day 7 1200 1400 900 1000 1350 1500 650 1700 1100 575 2500 6.25 9 9 5.0625 0.4444 0.6944 0 5.0625 9 8 16 8 4 5 4 5 5 4 5 START B 0 12 12 1 13 A 0 9 90 9 C018 18 0 18 Trial # E 12 18 6 13 19 D 9 18 99 18 G 18 24 6 20 26 F 18 24 6 19 25 H 18 24 6 18 24 Critical Path's before crashing LEGEND ID ES EF LS LF 124 31 725 32 K 24 32 8 24 32 Completion Time (before crashing) J 24 30 6 26 32 a) What is the probability that the project will take 30 to 37 days to complete? b) What project completion time should the project manager set as a goal to her team in order to be 87.50% confident that the project will be completed within that time frame? Your answer can be in days and you can provide the result in decimals. c) Suppose that for every day the project is shortened the maintenance firm will be awarded $3,500. What activities should be crashed and by how many days? Show your work using the table given below. At each trial reduce the project duration by one day stating which activity/ies should be crashed and how much it will cost to crash this activity/ies LINIS: Use the following table to answer. Add as many rows as you need and completely fill the table please H Activityles to be Crashed Crash Cost
Expert Answer:
Answer rating: 100% (QA)
ANSWER a To find the probability that the project will take 30 to 37 days to complete we need to calculate the probability of completion time between ... View the full answer
Related Book For
Operations and Supply Chain Management for the 21st Century
ISBN: 978-1111225292
1st edition
Authors: Ken Boyer, Rohit Verma
Posted Date:
Students also viewed these programming questions
-
You and a business partner opened a fitness gym three years ago. Your partner oversees managing the operations of the gym, ensuring the right equipment is on hand, maintenance is conducted, and the...
-
Accounting March February 6 7 8 9 Master Schedule for Day-Glo Solar Panels January 1 2. 3 4 5 120 95 100 120 135 140 102 125 115 120 165Solar panel product structure tree 1 Solar Panel Week...
-
This table contains 100 common words organized into a 10x10 grid. Each column and each row have headers listing Roman numerals. You are given a rowit and a columnt (using Arabic numerals.) You must...
-
Lamonda Corp. uses a job order cost system. On April 1, the accounts had the following balances: The following transactions occurred during April: (a) Purchased materials on account at a cost of...
-
What is integrated marketing communication? What are multi-channel promotional strategies? Why is word-of-mouth communication so important?
-
Investigate the asymptotic behavior of numerically and graphically: (a) Make a table of values of (x) for x = 50, 100, 500, 1000. (b) Plot the graph of . (c) What are the horizontal asymptotes of ?...
-
How is arbitration commenced?
-
Jeff Immelt became CEO and chairman of GE on September 7, 2001. Analyze GE's external environment since 2001 using PESTEL and discuss the effects these changes have had on GE. Is Immelt responsible...
-
Problem: Suppose that theexchange rate is 1.25 = 1.00. Options (calls and puts) are available on thePhiladelphia exchangein units of10,000 with strike prices of $1.60/1.00. Options (calls and puts)...
-
Carrie DLake, Reed A. Green, and Doug A. Divot share a passion for golf and decide to go into the golf club manufacturing business together. On January 2, 2020, DLake, Green, and Divot form the...
-
You are trying to estimate the cost of capital for La Coste, an upscale specialty retailer. The firm is in only one business, specialty retailing; comparable firms have an average published beta of...
-
Write down the stress matrix of the fluid cluster and its three invariants? Explain the physical meaning of the nominal pressure acting on the viscous fluid clusters? In the movement of viscous...
-
The sound velocity a in water is related to the volume modulus K and density . Use the Rayleigh method to derive the sound velocity expression.
-
Please indicate the main measures to reduce the resistance of low-speed objects moving around the flow?
-
What is the linearized equation for the velocity potential function of compressible potential flow? Please describe the linearization conditions.
-
Derive a differential equations that describes the motion of an ideal compressible fluid.
-
A florist determines the probabilities for the number of flower arrangements they deliver each pa number in the boom Part 1: 4 points day. Part 2: 4 points Part 3: 2 points D) Part 4: 2 points 12...
-
Data 9.2 on page 540 introduces the dataset Cereal, which includes information on the number of grams of fiber in a serving for 30 different breakfast cereals. The cereals come from three different...
-
A quick service restaurant is considering changing the number of process steps necessary in assembling a burger. Currently the burger assembly process requires four steps, each of which operates at...
-
A product has the following demand history for the past six months: January.............................. 212 February............................. 201 March................................ 242...
-
Given the data in Table 5.22, compute the forecast error measurements indicated. 83 2. 4. 11 9 5 4 7 508 354 2 18 88599 541. 31 478 3 354 08 25 35 01 01 60 76 06 03 62 555 1 01 2 123456789
-
Marsha Solomon, a physiotherapist, opened a practice. The business completed the following transactions: After these transactions, how much cash does the business have to work with? Use T-accounts to...
-
Refer to Exercise 2-3. Which of the transactions of Marsha Solomon, P.T., increased the total assets of the business? For each transaction, identify the asset that was increased or decreased....
-
Assume that Lululemon Athletica Inc. reported the following summarized data at December 31, 2020. Accounts appear in no particular order; dollar amounts are in millions. Prepare the trial balance of...
Study smarter with the SolutionInn App