1. If the demand per day is 100 , the lead time is 5 days, safety stock is 50 , and the container size is 55 , what is the Kanban number? If the lead time improves to 4 days, what is the Kanban number?
2. The demand for milk at a coffee shop is 60 quarts per day. Lead time to replenish inventory is 2 days and the coffee shops want to have1/2of safety stock. If the container size of milk is 10 quarts, what is the Kanban number?