You are working in Charlene & Gillian (C&G) consultant QS Ltd. You are appointed as a...
Fantastic news! We've Found the answer you've been seeking!
Question:
Transcribed Image Text:
You are working in Charlene & Gillian (C&G) consultant QS Ltd. You are appointed as a contractor administrator in a project owned by Nicolas and Faye (N&F) Developers Ltd. to renovate a clubhouse located at the penthouse of a luxurious service apartment at 883 Latrobe Street, Melbourne. The following are the relevant contract particulars: Original Contact Sum: $10 Million Original Contract Period: 12 months Contract Commencement Date: 1/10/2019 Contract Date for Completion: 30/9/2020 Liquidated and Ascertained Damages: $2000/day By June 2020, the Contractor (Manifolds Contracting Co. Ltd.) had been in serious delay (through his own default) with no entitlement to an extension of time. According to the revised programme submitted by Manifolds on 15/6/2020, his anticipated date for completion of the contract was 30/11/2020, i.e. two months delay was anticipated. The Superintendent had endorsed the revised programme after the examination. On 22/6/2020, unfortunately, there were suspected cases of Coronavirus amongst the residents of the lower floors of the building. The building was subject to tight ingress/egress control by the Health Department waiting for medical diagnosis of the patients. No construction work was possible during the control period. The patient's illnesses were later confirmed NOT relating to Corona Virus and the control was lifted on 20/8/2020. The percentage value of work completed upon suspension of work was 70% of the original contract sum. By June 2020, the Contractor (Manifolds Contracting Co. Ltd.) had been in serious delay (through his own default) with no entitlement to an extension of time. According to the revised programme submitted by Manifolds on 15/6/2020, his anticipated date for completion of the contract was 30/11/2020, i.e. two months delay was anticipated. The Superintendent had endorsed the revised programme after the examination. On 22/6/2020, unfortunately, there were suspected cases of Coronavirus amongst the residents of the lower floors of the building. The building was subject to tight ingress/egress control by the Health Department waiting for medical diagnosis of the patients. No construction work was possible during the control period. The patient's illnesses were later confirmed NOT relating to Corona Virus and the control was lifted on 20/8/2020. The percentage value of work completed upon suspension of work was 70% of the original contract sum. On 21/8/2020, N&F, after reviewing the situation, instructed the contractor via the Superintendent to continue the suspension of the work until 22/9/2020. The work restarted on 23/9/2020. Today is 31/3/2021, your boss has just sent you an e-mail and asked you to respond to the following questions: [a] Calculate the liquidated damages that Manifolds should compensate N&F. Work out the details by citing relevant clause(s) from AS2124. (4 marks) [b] State, with the relevant AS2124 contract clause and sub-clause, the period(s) of delay that N&F should pay loss and expenses to Manifolds? (3 marks) [c] State, with the relevant AS2124 contract clause and sub-clause, which period(s) of delay should be regarded as 'neither party's fault', and cite relevant clause(s) from the AS2124. (3 marks) HTML BEY You are working in Charlene & Gillian (C&G) consultant QS Ltd. You are appointed as a contractor administrator in a project owned by Nicolas and Faye (N&F) Developers Ltd. to renovate a clubhouse located at the penthouse of a luxurious service apartment at 883 Latrobe Street, Melbourne. The following are the relevant contract particulars: Original Contact Sum: $10 Million Original Contract Period: 12 months Contract Commencement Date: 1/10/2019 Contract Date for Completion: 30/9/2020 Liquidated and Ascertained Damages: $2000/day By June 2020, the Contractor (Manifolds Contracting Co. Ltd.) had been in serious delay (through his own default) with no entitlement to an extension of time. According to the revised programme submitted by Manifolds on 15/6/2020, his anticipated date for completion of the contract was 30/11/2020, i.e. two months delay was anticipated. The Superintendent had endorsed the revised programme after the examination. On 22/6/2020, unfortunately, there were suspected cases of Coronavirus amongst the residents of the lower floors of the building. The building was subject to tight ingress/egress control by the Health Department waiting for medical diagnosis of the patients. No construction work was possible during the control period. The patient's illnesses were later confirmed NOT relating to Corona Virus and the control was lifted on 20/8/2020. The percentage value of work completed upon suspension of work was 70% of the original contract sum. By June 2020, the Contractor (Manifolds Contracting Co. Ltd.) had been in serious delay (through his own default) with no entitlement to an extension of time. According to the revised programme submitted by Manifolds on 15/6/2020, his anticipated date for completion of the contract was 30/11/2020, i.e. two months delay was anticipated. The Superintendent had endorsed the revised programme after the examination. On 22/6/2020, unfortunately, there were suspected cases of Coronavirus amongst the residents of the lower floors of the building. The building was subject to tight ingress/egress control by the Health Department waiting for medical diagnosis of the patients. No construction work was possible during the control period. The patient's illnesses were later confirmed NOT relating to Corona Virus and the control was lifted on 20/8/2020. The percentage value of work completed upon suspension of work was 70% of the original contract sum. On 21/8/2020, N&F, after reviewing the situation, instructed the contractor via the Superintendent to continue the suspension of the work until 22/9/2020. The work restarted on 23/9/2020. Today is 31/3/2021, your boss has just sent you an e-mail and asked you to respond to the following questions: [a] Calculate the liquidated damages that Manifolds should compensate N&F. Work out the details by citing relevant clause(s) from AS2124. (4 marks) [b] State, with the relevant AS2124 contract clause and sub-clause, the period(s) of delay that N&F should pay loss and expenses to Manifolds? (3 marks) [c] State, with the relevant AS2124 contract clause and sub-clause, which period(s) of delay should be regarded as 'neither party's fault', and cite relevant clause(s) from the AS2124. (3 marks) HTML BEY
Expert Answer:
Answer rating: 100% (QA)
Answer a Liquidated damages that Manifolds should compensate NF According to clause 451 of AS2124 the contractor is liable for liquidated damages at the rate of 2000 per day for any delay in completio... View the full answer
Related Book For
Posted Date:
Students also viewed these medical sciences questions
-
You are working in Mexico City on an assignment for one year. You are being trained in the Mexican sales department of a U.S. medical instrument company. You are excited because you are about to bid...
-
You are working in the office of the vice president of administration at International Telecon (IT) as a senior financial planner. IT is a Fortune 500 firm with sales approaching $ 1 billion. IT...
-
You are working in the office of a precious metals buyer. A miner brings you a nugget of metal that he claims is gold. You suspect that the metal is a form of fools gold, called marcasite, that is...
-
Assume you are considering opening a retail business. You are trying to decide whether to have a traditional brick-and-mortar store or to sell only online. Explain how the activities and costs differ...
-
Use a power series to approximate the definite integral to six decimal places. a. b. 0.1 x arctan(3x) dx
-
Pick a product like Cadillac or Sara Lee Deli products or service like Mr. Clean Performance Car Wash or a car and home insurance company that is offered in a limited number of countries. Assess the...
-
An airplane flies at a speed of \(400 \mathrm{mph}\) at an altitude of \(10,000 \mathrm{ft}\). If the boundary layers on the wing surfaces behave as those on a flat plate, estimate the extent of...
-
Camp Manufacturing turns over its inventory eight times each year, has an average payment period of 35 days, and has an average collection period of 60 days. The firms annual sales are $3.5 million....
-
Write a program that prompts the user to enter a phrase and then prints out the ASCII code of each character in the phrase. A sample run of your program should look like: Enter a phrase: I love...
-
Since the early 1990s, woodstove sales have declined from 1,200,000 units per year to approximately 100,000 units per year. The decline has occurred because of (1) stringent new federal EPA...
-
Addresses the relationship between corporations and their customers. Many ethical considerations form the basis of that relationship and all of us, as consumers are aware of the good, the bad, and...
-
(a) Explain briefly two ways in which the details of account balances may be tested; and (b) For each of these ways, explain the circumstances in which its use is particularly appropriate.
-
In identifying the value stream, why is it important to go beyond the boundaries of the organization of interest?
-
A defense contractor is bidding on a military contract for 100 radar units. The contractor employs 30 machine operators who work 165 hours a month each. The first radar unit required 1145 operator...
-
With single sourcing, how does the firm protect itself from price gouging? From strikes or interruptions to supply?
-
The Certified Fraud Examiner has a code of ethics which he must abide. Briefly describe the eight ethical principals that a fraud examiner should follow.
-
Find the Laplace transform of the function ( f(t) = e^{3t} \cos(2t) ). Use the transform to solve the differential equation ( y - 6y + 13y = 0 ) with initial conditions ( y(0) = 0 ) and ( y(0) = 1 ).
-
Baxter, Inc., owns 90 percent of Wisconsin, Inc., and 20 percent of Cleveland Company. Wisconsin, in turn, holds 60 percent of Clevelands outstanding stock. No excess amortization resulted from these...
-
Calculate the heat of vaporization, Hovap, of water, using standard enthalpies of formation (Table 6.2). 14270 8 099 0740 9 6416 3818 02015 0 or Hj H Si Si Si Si Si Si A A A A A A So Na Na Na Na Na...
-
Give equations for (a) The first transmutation of an element obtained in the laboratory by nuclear bombardment, and for (b) The reaction that produced the first artificial radioactive isotope.
-
Find the concentrations of Ag+(aq), NH3(aq), and [Ag(NH3)2]+(aq) at equilibrium when 0.10 mol Ag+(aq) and 0.10 mol NH3(aq) are made up to 1.00 L of solution. The dissociation constant, Kd, for the...
-
An additive having a viscosity of $2 \mathrm{cP}$ and a density of $50 \mathrm{lb}_{\mathrm{m}} / \mathrm{ft}^{3}$ is fed from a reservoir into a mixing tank. The pressure in both the reservoir and...
-
You must determine the pump head and power required to transport a petroleum fraction $(\mu=$ $\left.60 \mathrm{cP}, ho=55 \mathrm{lb}_{\mathrm{m}} / \mathrm{ft}^{3} ight)$ at a rate of $500...
-
A pump takes water from a reservoir and delivers it to a water tower. The water in the tower is at atmospheric pressure and is $120 \mathrm{ft}$ above the reservoir. The pipeline is composed of $1000...
Study smarter with the SolutionInn App