ash the network schedule given in figure 2 and find the optimum time and the least total
Fantastic news! We've Found the answer you've been seeking!
Question:
ash the network schedule given in figure 2 and find the optimum time and the least total cost. Indirect cost = $ 150/day.
Activity | Duration | Direct Cost ($) | ∆ Cost | ∆ Day | ∆ Cost /day | Days shortened | |||||||
Normal | Crash | Normal | Crash | Cycle 1 | Cycle 2 | Cycle 3 | Cycle 4 | Cycle 5 | |||||
A | 3 | 2 | 500 | 550 | |||||||||
B | 4 | 3 | 300 | 400 | |||||||||
C | 5 | 3 | 200 | 380 | |||||||||
D | 8 | 7 | 700 | 820 | |||||||||
E | 7 | 7 | 300 | 300 | |||||||||
F | 9 | 7 | 200 | 550 | |||||||||
Days cut | |||||||||||||
Project Duration | |||||||||||||
Increased cost/day | |||||||||||||
Total Direct cost | |||||||||||||
Total Indirect cost | |||||||||||||
General Total Cost |
Q. 1. Find the optimum duration.
15 days
18 days
20 days
13 days
Q.2. Find the minimum cost.
$4,590
$4,680
$4,850
$4,120