Question: ackboard > XC Remaining Time: 1 hour, 53 minutes, 19 seconds. Question Completion Status: QUESTION 18 18 20 Ps are needed in the following product-tree,
ackboard > XC Remaining Time: 1 hour, 53 minutes, 19 seconds. Question Completion Status: QUESTION 18 18 20 Ps are needed in the following product-tree, and on-hand inventory consists of 10 As, 15 Bs. 20 Cs, 12 Ms, and 5 Ns, how many Cs are needed? A (2) B (3) M(3) N (4) C (4) D (5) 48 144 192 212 240 QUESTION 10 Durand for an emis 26 000 iveals lead-time is 4 days and salt 2 ust. Assume 250 rue water ckboard XCO A Remaining Time: 1 hour, 53 minutes, 12 seconds. Question Completion Status: QUESTION 19 Demand for an item is 36,000 units per year, its lead-time is 4 days, and safety stock is 24 units. Assuming 250 working days per year what is the reorder point for this Item? (Link to Formulas.Z.Table & Excel Worksheet) 100 units 200 units 300 units 600 units 700 units QUESTION 20 ABC analysis is based upon the principle that All items in Inventory must be monitored very dosely There are usually a few critical hems, and many tems that are less critical An item is critical if its usage is high More time should be spent on class "C"Items because there are many more of them As with grade distributions in many MBA courses, there should be more medium level items than her "A" or "turns QUESTION 21 Uber receives multiple complaints per day about their drivers behavior over 9 days the Uber in San Diego recorded the number of can "kboard XC Remaining Time: 1 hour, 53 minutes, 05 seconds. Question Completion Status: Uber receives multiple complaints per day about their drivers' behavior. Over 9 days the Uber in San Diego recorded the number of calls to be 3.0.8.9.6.7.49 and 8 What is the lower controllimit for the 3-sigma c-chart? Link to Formulas.Z.Table & Excel Worksheet) 2.45 13.35 0.00 8.45 9.03 QUESTION 22 Which of the following are the primary functions of all organizations? Engineering, Marketing Sales and Finance/Accounting Engineering Production Operations, and Finance Marketing Sales Production/Operations and Finance Accounting Engineering Marketing Sales and Production Operations Human Resources. Production Operations, and Finance/Accounting QUESTION 23 The demand forecast for a certain product is 7000 units per year. The product follows a seasonal pattern for which the January 12. hehe Seasonally adjusted sales forecast for January QUESTION 1 As discussed at our lectures about Supply Chain Management, Key performance measures for Make-to-Stock items include all, except Inventory Turnover Shrinkage Rate Inventory Replenishment Time Time to Fill Back Orders Percentage of On-Time Promised Orders Completed QUESTION 2 A project being analyzed by PERT has 27 activities, 15 of which are on the critical path. If the estimated time along the critical path is 100 days and the project variance is 16 days, with 99% confidence, when would the project get completed? (Link to Formulas.Z.Table & Excel Worksheet) 8495 100 112 109 137 QUESTIONS