Question: ACQ 202. DAU University. Designing. -Protyping the System A program office for a command and control system needs to prepare a Statement of Work (SOW)
ACQ 202. DAU University. Designing. -Protyping the System
A program office for a command and control system needs to prepare a Statement of Work (SOW) that lays out the products to be delivered and the technical reviews to be held by the contractor. Which tool would they most likely use?
1. Technical Performance Measure (TPM)
2. Work Breakdown Structure (WBS)
3. Modeling and Simulation
4. Trade Studies