Question: ACQ101 Module 7 - Help me to select the correct answer to the question. The four choices are listed below question. Thanks. What cost estimating
ACQ101 Module 7 - Help me to select the correct answer to the question. The four choices are listed below question. Thanks.
What cost estimating technique would be indicated for the following situation? The program is early in the Engineering and Manufacturing Development phase. An estimate is needed quickly to support a "what-if" discussion. A moderate degree of subjectivity can be accommodated. A good database exists with information on many similar systems and their performance characteristics.
Engineering
Parametric
Analogy
Actual Cost