Question: Activities A , B , C , and D , with durations 7 , 1 2 , 9 , and 6 respectively, are all connected
Activities and with durations and respectively, are all connected with starttostart relationships. There are days of lag from B to and day from to D Develop the network diagram and calculate the CPM values, show them on the diagram, and indicate all critical activities. Also, indicate the project duration.
Activities A B E and F with durations and respectively, are all connected with finishtofinish relationships. There are days of lag from to and day from to F Develop the network diagram and calculate the CPM values, show them on the diagram, and indicate all critical activities. Also, indicate the project duration.