Question: Activities A , B , C , and D , with durations 7 , 1 2 , 9 , and 6 respectively, are all connected

Activities A,B,C, and D, with durations 7,12,9, and 6 respectively, are all connected with start-to-start relationships. There are 2 days of lag from B to C and 1 day from C to D. Develop the network diagram and calculate the CPM values, show them on the diagram, and indicate all critical activities. Also, indicate the project duration.
Activities A, B, E, and F, with durations 2,7,10, and 3 respectively, are all connected with finish-to-finish relationships. There are 4 days of lag from A to B and 1 day from E to F. Develop the network diagram and calculate the CPM values, show them on the diagram, and indicate all critical activities. Also, indicate the project duration.
 Activities A,B,C, and D, with durations 7,12,9, and 6 respectively, are

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!