Question: Activities C , D , and E in the project represented by the network above are to be hammocked. What is the activity length of

Activities C, D, and E in the project represented by the network above are to be hammocked. What is the activity length of the hammock activity shown above? (1 mark)
A)20
B)16
C)13
D)11
Answer: 20
Activities C, D, and E in the project represented by the network are to be hammocked. What are the early start and late finish times of the hammock activity? (1mark)
A)6,20
B)6,26
C)9,20
D)9,26
Answer:
 Activities C, D, and E in the project represented by the

Step by Step Solution

There are 3 Steps involved in it