Question: Activities can be delayed only to the point where all their positive slack is used up, as any further delays would cause the project to
Activities can be delayed only to the point where all their positive slack is used up, as any further delays would cause the project to Option A increase costs of all the activities in the project. Option B extend beyond the project completion time. Option C be completed ahead of schedule. Option D increase its requirements for additional resources for all activities